CONSTRUCTION PROGRESS
Phase 1 - Under Construction (77% as at March 2024)
PROJECT UPDATE
Currently, construction is focusing on the architectural, mechanical and electrical works, beam and slab for Tower A & Tower B, as well as the upper roof and installation of water tank for Tower C.
TARGET COMPLETION DATE
Phase 1 - 1 August 2025