CONSTRUCTION PROGRESS
Phase 1 – Under Construction (98% as at June 2024)
PROJECT UPDATE
All physical works for the building and defect rectification in Zone A have been completed. Currently, construction is focusing on external infrastructure works, such as retaining wall and road widening works, as well as building rectification works in Zone B. Concurrently, the contractor has submitted a work permit to Jabatan Kerja Raya (JKR) and aims to obtain the official permit for external water reticulation works by mid-July 2024.
TARGET COMPLETION DATE
Phase 1 – Quarter 3 of 2024