CONSTRUCTION PROGRESS
Phase 1 – Under Construction (98% as at July 2024)
PROJECT UPDATE
Building rectification works at Zone A have been completed. Currently, construction is focusing on external infrastructure works, including the retaining wall and road widening, as well as building rectification works at Zone B. Concurrently, the contractor has submitted a work permit to Jabatan Kerja Raya (JKR) and aims to obtain the official permit for external water reticulation works by the end of August 2024.
TARGET COMPLETION DATE
Phase 1 – Quarter 3 of 2024