CONSTRUCTION PROGRESS
Phase 1 – Under Construction (97% as at March 2024)
PROJECT UPDATE
All physical works at the site have been completed. Currently, construction is focusing on completing infrastructure works including water reticulation works at the main road, upgrading the main access road, telecommunications work, water tank and defect rectification works. The contractor has also commenced engagement with Majlis Perbandaran Kulim Kedah (MPKK) and technical agencies for the Certificate of Completion & Compliance (CCC) inspection process.
TARGET COMPLETION DATE
Phase 1 – Quarter 2 of 2024