CONSTRUCTION PROGRESS
Under Construction (99% as at March 2024)
PROJECT UPDATE
Physical works for buildings and internal infrastructure have been completed. Currently, construction is focusing on defect rectification, cleaning and external infrastructure works. Concurrently, a final inspection with Majlis Bandaraya Melaka Bersejarah (MBMB) and technical agencies has been scheduled throughout April 2024 to obtain the remaining 6 supporting letters for the Certificate of Completion & Compliance (CCC).
TARGET COMPLETION DATE
Quarter 2 of 2024