CONSTRUCTION PROGRESS
Phase 1 – Under Construction (99% as at Mac 2024)
PROJECT UPDATE
All physical works at the site have been completed. Currently, construction is focusing on defect rectification and cleaning works. The final inspection with Majlis Daerah Pasir Putih (MDPP) and technical agencies has been scheduled throughout April 2024 to obtain the remaining 9 supporting letters for the Certificate of Completion & Compliance (CCC).
TARGET COMPLETION DATE
Phase 1 – Quarter 2 of 2024