CONSTRUCTION PROGRESS
Phase 1 – Under Construction (99% as at June 2024)
PROJECT UPDATE
All physical works for buildings and internal infrastructure have been completed. The remaining work focuses on addressing comments from IWK. The final inspection with Majlis Daerah Pasir Puteh (MDPP) and Jabatan Kerja Raya (JKR) will be conducted upon acceptance of the sewerage rectification works by IWK, targeted for mid-July 2024
TARGET COMPLETION DATE
Phase 1 – Quarter 3 of 2024